The existing Terminal A is a terminal / concourse facility connected to, and immediately north of the existing FIS facility and the North Concourse project, which is currently under construction by others. Currently Terminal A is a two-level facility that supports 17 aircraft gates and contains ticketing, security screening, concessions, passenger departure areas, baggage handling and airline operations facilities. The Terminal A Modifications and BHS scope of the TAIP will expand the existing facility by approximately 62,000 SF, enhance functionality and passenger experience by renovating 45,000 SF of the existing space, as well as provide a new automated in-line baggage handling system. The expansion areas will contain new ticketing halls, restrooms, concessions and passenger departure areas. The new single story ticketing halls will be constructed on the land side of the existing Terminal, to the north and south of the vertical circulation core, and account for approximately one-third of the building expansion. The balance of the 62,000 SF expansion is a two story addition on the airside of the terminal between the existing boarding bridges for gates A3 & A7. The new airside expansion will contain an open concessions area with views of the airfield and passenger departure areas on the second level. The ramp level of the airside addition will provide space for inbound and outbound baggage make-up operations.

Terminal A Rendering

The existing ticketing hall and airline support offices on the second level will be transformed into a highly efficient centralized security screening area which will support increased passenger projections through follow-on phases of the Airport Expansion Program. The new security screening area accounts for approximately 18,000 SF of the renovations. The balance of the renovations will provide additional concessions space on level two along with reconfigured airline operations areas on Level 1 that will better support the increased functionality for Terminal A.

The Terminal A portion of the Terminal Area Improvement Program will include unique challenges and require close coordination to maintain an operational Terminal through the 21 months construction process.  Accordingly the construction will be performed in phases and work will be performed on day & night shifts depending on the area and type of construction being performed.  In addition the work will require daily coordination with the airlines and airport operations personnel along with a strong commitment to maintaining an acceptable level of customer satisfaction for the traveling public.

Bid Package #1 - EDS Screening Building

The Bid Package #1 scope encompasses the work necessary to construct a Design-Build 2,700 SF interim building shell that will house four EDS machines for a duration of 2 years.  Listed below is the subsystem scope of work that was bid and significant dates in the process:

1A   Complete Design-Build structure including framing, insulation, sheathing, hollow metal doors & frames, hollow metal sliding doors and roofing

 

Package Release Date >> May 23, 2007

Bid Package #1 Specific Documents >> No longer Available

Bid Received >> June 21, 2007 at 2:00 PM (PDT)

Bid Results >> Available For Review

Bid Package #2 -

Escalators and Service Elevator
Emergency Exit Stairs and Material Receiving Area

Bid Package No. 2’s scope encompasses the work necessary to construct the new emergency exit stairs along with the core & shell of the ticket lobby restrooms that are located directly beneath the stairs.  In addition, this bid package includes work for a new service elevator and material receiving area located at the north end of Terminal A on the airside. The scope of work includes demolition, new construction and remodeling of existing space to accommodate these new functions.  Listed below are the subsystems that were bid and significant dates in the process:

   Sub-Package #2.1 - Elevators & Escalators

 

2.1A   Elevators & Escalators

 

Package  Release Date >> July 27, 2007

Bid Package #2.1 Specific Documents >> No Longer Available

Bids Received >> August 15, 2007 at 2:00 PM (PDT)

Bid Results >> Available For Review

   Sub-Package #2.2 - Balance of Package #2

 

2.2A   Building & Selective Demolition

2.2B   Form, Place and Finish Cast-In-Place Concrete Walls & Stairs

2.2C   Concrete & CMU Reinforcing

2.2D   CMU

2.2E   Misc. Metals & Ornamental Metals

2.2F   Chain Link Fencing & Gates

2.2G   Waterproofing & Joint Sealants

 

Package Release Date >> August 1, 2007

Bid Package #2.2 Specific Documents >> No Longer Available

Bid Received >> August 21, 2007 at 2:00 PM (PDT)

Bid Results >> Available For Review

Bid Package #3 - Superstructure and Foundations for Ticket Lobbies & Airside Expansion

The Bid Package #3 scope encompasses the work necessary to complete the superstructure, foundations and roofing for the building additions. The landside additions total 22,000 SF of single story structure while the airside addition represents 20,000 SF of new two story building footprint.  Listed below are the subsystems that were bid and significant dates in the process:

3A   Structural Steel & Miscellaneous Metals

3B   Metal Decking

3C   Concrete Materials

3D   Concrete Reinforcing

3E   Fireproofing

 

Package Release Date >> September 20, 2007

Bid Package #3 Specific Documents >> No longer Available

Bids Received >> November 6, 2007 at 2:00 PM (PST)

Bid Results >> Available For Review

Bid Package #4 - EDS Screening Building Baggage Handling System

The Bid Package #4 scope is made up of a single subsystem to provide a temporary outbound conveyor system and make-up device for the temporary EDS screening building. Listed below is the subsystem scope of work that was bid and significant dates in the process:

4A   Baggage Handling System

 

Package Release Date >> September 20, 2007

Bid Package #4 Specific Documents >> No longer Available

Bids Received >> November 6, 2007 at 2:00 PM (PST)

Bid Results >> Available For Review

Bid Package #5 - Interior & Exterior Assemblies

The Bid Package #5 scopes of work  includes subsystems required to begin the process of creating both interior and exterior spaces at Terminal A and initial finish work required for the mechanical, plumbing and electrical trades to complete rough-in activities.  Listed below are the subsystems that were bid and significant dates in the process:

5A   Selective Building Interior Demolition

5B   Expansion Joint Covers

5C   Building Insulation

5D   Roofing

5E   Flashing and Sheetmetal

5F   Hollow Metal Doors, Frames and Hardware

5G  Drywall, Metal Stud Framing and Related

5H   Portland Cement Plaster

5I    Acoustical Ceilings

5J   Specialty Ceilings

 

Package Release Date >> April 15, 2008

Pre-qualification Statement >> Must be submitted by April 29, 2008

Pre-Proposal Conference >> April 24, 2008 at 10:00 AM (PDT)

Bid Package #5 Specific Documents >> No Longer Available

Bid Received >> May 13, 2008 at 2:00 PM (PDT)

Bid Results >> Available For Review

Bid Package #6 - Interior Finishes

The Bid Package #6 scopes of work include architectural finishes which create much of the finished look and feel for the interior of Terminal A project.  Listed below are the subsystems that were bid and significant dates in the process:

6A   Polished Concrete

6B   Column Covers, Stainless Steel Base, Stainless Steel Wainscot & Rolling Security Screens

6C   Glass Railings

6D   Terrazzo Flooring

6E   Carpet & VCT Flooring

6F   Painting & Coatings

 

Package Release Date >> May 1, 2008

Pre-Proposal Conference >> May 9, 2008 at 10:00 AM (PDT)

Pre-qualification Statement >> Must be submitted by Late April 2008

Bid Package #6 Specific Documents >> No Longer Available

Bids Received >> May 22, 2008 at 2:00 PM (PDT)

Bid Results >> Available For Review

Bid Package #7 - Consolidated Woodwork and Signage

Bid Package #7 is comprised of architectural woodwork and signage subsystems for the entire project which is made up of Terminal A, Terminal A Plus, Terminal B and the North Concourse.  Listed below are the subsystems that are being bid and significant dates in the process:

7A   Terminal A and A Plus Architectural Woodwork

7B   Terminal A Signage

7C   Terminal B and North Concourse Architectural Woodwork

7D   Terminal B and North Concourse Signage

 

Package Release Date >> July 31, 2008

Pre-Proposal Conference >> August 12, 2008

Pre-qualification Statement >> Must be submitted by Mid August 2008

General Bid Documents >> Available for Downloading

Bid Package #7 Specific Documents >> Available for Downloading

Bids Received for Architectural Woodwork >> September 4, 2008 at 2:00 PM (PDT)

Bid Date for Signage >> September 30, 2008 at 2:00 PM (PDT)  

Other Documents

Please refer to the Drawings and Specs page for information on obtaining drawings and specifications for any of the bid packages.  Narratives for all Addenda related to Terminal A Modifications packages will be posted the day of issue at the Terminal A Modifications Bid Documents page and drawings will be available the same day from the printing vendor.

All inquires related to the Terminal A Modifications bid process should be directed to tam@sjctaip-opportunities.com.